Daily Report — Kessler Residence Remodel

Project
Kessler Residence — Phase 2
Address
2118 E Glenrosa Ave, Phoenix AZ 85016
Day on site
Day 9 of 14
Weather AM
Clear · 71°F · wind 4 mph
Weather PM
Sunny · 94°F · wind 8 mph
Hours on site
6:30 AM – 3:15 PM

Crew

Work performed

Continued framing on east-side bathroom rebuild. Installed king and jack studs around new shower opening per revised plan rev. C. Set blocking for floating vanity and grab bars. Ran 12/2 NM-B from sub-panel to GFCI on north wall (rough-in only; not energized). Verified plumb on shower wall to 1/16 in. Cleaned site at 3:00 PM, hauled drywall scrap to dumpster.

Delays / issues

Materials & equipment

Safety notes

Tailgate safety meeting 6:35 AM — focus on ladder positioning per OSHA 4:1 rule after near-miss on Day 7. All crew confirmed. No incidents today.

Shower opening framed (south wall)
Sub-panel rough-in, GFCI run
Floating vanity blocking, plumb to 1/16"
R. Briones
Site lead — Roberto Briones
 